Southern Middle Back Ranges – Primary Crusher Reline

Southern Middle Back Ranges – Primary Crusher Reline

Southern Middle Back Ranges

Primary Crusher Reline

The Primary Crusher on this site has traditionally used scaffolding as the only method of access to change the liners. The construction of the scaffold had proven to be time-consuming and left very little time to complete the change of the liners.

This required the maintenance on this primary crushing bin to be ongoing with only a few liners changed. Using rope access methods, Tasman entered this bin in July 2019 for the 1st of a 2-stage complete liner change. We successfully changed the North, East, and South liners over 2 x 42hr shutdowns, bringing the crusher back to new wall condition.

The client has been able to run the Primary Crusher at full capacity without building scaffolds or changing wall liners between October 2019 and October 2021. This has proven to be a significant cost-saving exercise for the client over that period.

Get In Touch

Get In Touch

We welcome any opportunity to form a valuable and ongoing partnership with your company.

Contact Us